Determine the functional requirements of the product, as well as the initial formulation requirements direction
1 round of product proofing time 3 days, according to the proofing demand adjustment, proofing time increases
Confirmation of the recipe, the design of the consumables and the payment in advance
Such as: bags - cans - boxes - rolls of film, etc., the work period including constraints version of about 20-25 days
The raw materials have been purchased in the process of package customization in the previous period, except for special raw materials, start batching - feeding production - packaging - storage in about 20 days
Payment of the remaining balance, delivery after receipt, products out of the warehouse - logistics in transit 1-7 days, depending on the region